NCDOT provides construction update on Rodanthe bridge
Getting your Trinity Audio player ready… Actual construction of the Rodanthe bridge is 47% complete. NCDOT held a virtual quarterly update meeting on bridge project, which is scheduled to open for traffic in the fall of 2021. At the Sept. 3 meeting, resident engineer Pablo Hernandez reported that 52 of the 108 bents have been … Continue reading NCDOT provides construction update on Rodanthe bridge